Project description

When completed in 2014, the Wasit Gas Plant became one of the largest gas plants Saudi Aramco had ever built. The program also provided for installing natural gas liquids (NGL) fractionation facilities inside the Wasit central processing facility to process a C2+ NGL stream produced at Khursaniyah. Saipem was awarded the installation of the subsea pipelines. Saipem in their turn subcontracted Boskalis for the dredging and landfall works.

Bezemer was contracted to supply the pull-in equipment and the wire lay spread, the special wires were supplied by Saipem. For this project Bezemer used the KTC 400 linear winch to pull the 3.500-meter-long pipelines. In total 3 pipelines were pulled in 2 dredged trenches.