In May 2013 Geocean has completed the prefabrication, installation and pre-commissioning of 1×14″ and 1×16″ pipelines, 850m long each, at Addah (Ivory Coast).
Installation has been performed by pulling the pipes from shore using an intermittent pulling winch, 12 mTon Stevshark anchor and 2400 meters of 52mm. steel wire.
For this project, Bezemer supplied the linear winch, wires, sheaves, etc.
The winch used, was an intermittent linear winch, type CLI 210. The small dimensions and low weight made it the best solution for this project.